Welcome to the construction archive of Secret Weapon 6! Here you can take a look back at the coverage TowersTimes provided of TH13TEEN, from initial work starting in March 2009, to the ride nearing completion in February 2010.
- 28th March 2009
- 3rd May 2009
- 26th May 2009
- 22nd June 2009
- 11th July 2009
- 20th July 2009
- 10th August 2009
- 17th August 2009
- 14th September 2009
- 20th September 2009
- 27th September 2009
- 1st October 2009
- 3rd October 2009
- 5th October 2009
- 7th October 2009
- 11th October 2009
- 14th October 2009
- 17th October 2009
- 27th October 2009
- 28th October 2009
- 9th November 2009
- 2nd December 2009
- 4th December 2009
- 17th December 2009
- 20th December 2009
- 6th January 2010
- 13th January 2010
- 31st January 2010
- 13th February 2010
On 12th March 2009, Alton Towers Resort’s new rollercoaster for the 2010 season was approved by Staffordshire Moorlands District Council. The ride, which replaced Corkscrew, was dubbed to have world first features and was codenamed “Secret Weapon Six”.
These initial photos show the last remaining pieces of Corkscrew being removed, and the area prepared for new construction. The majority of the ride was transportable, so no large footers or foundations had to be removed. The iconic double inversion track sections were shipped off to a contractor to be refurbished into a new landmark feature for the main entrance of the theme park. Most of the queue line for Corkscrew was retained for the new attraction.
A large banner sign was erected at the edge of the site, featuring sinister artwork and the words “ Yet another fantabulous Alton Towers Resort development coming 2010”.
Land clearing started to take place in the woods behind the main construction site in preparation for the footers for the track layout in this section. Station area foundation work continued with the creation of formwork, which is used by manufacturing moulds made out of wood, onto which concrete is poured.
The first delivery of ride parts from Switzerland and Lichenstein based Intamin took place. This consisted of track for the station, maintenance area and first curve before the lift hill, along with nuts, bolts, and parts for the ride control system. Ride Construction Service Worldwide (RCS) were installing the ride, and their first shipping containers also arrived at the resort.
Further deliveries of ride parts took place from Intamin, including air tanks, compressors, and many more track sections. On site, vertical construction has commenced with the maintenance area track supports being installed. The supports for this particular model of coaster are not bolted to a footer, instead they are sunken within it, and then concrete poured into the mould to secure it in place.
As part of a wider marketing campaign, the secret element was finally delivered on to the construction site. The resort were not yet ready to announce exactly what it was, so had the element wrapped in a large cover, adorning the words “AUTHORISED PERSONNEL ONLY and SECRET WEAPON INSIDE”. Although to enthusiasts it was now obvious that the element was a drop track, the campaign certainly got people speculating about exactly what it could be.
Who cares about a snowman when you can build a rollercoaster? A large amount of snowfall is always a hindrance to construction projects, but the resort took the opportunity to promote TH13TEEN, which had now officially been announced. Some of the constructions workers built a replica of the front car in snow, and then took a ride themselves!
As part of the transition from Ug Land to Dark Forest, TH13TEEN’s neighbour Rita received a spooky makeover. Gone were the bright colours, race track theming and any trace of dinosaurs. The control cabin, trains, bunker, and entrance arch all received updates to ensure they would fit in the new area.